Chimney Project Stretches Contractor’s Work To New Heights

Tweet Garot Mechanical replaced the top 40 feet of this boiler stack for Green Bay Packaging.
Tweet Garot Mechanical replaced the top 40 feet of this boiler stack for Green Bay Packaging.

With welding done from a basket perched high on the largest crane in Wisconsin, Tweet-Garot Mechanical Inc. of Green Bay, Wis. recently installed the top 40 feet of a coal-fired boiler stack for the Green Bay Packaging paper mill. At times the work must have seemed like a high-wire balancing act because of the towering heights and tight timeframe involved.

The mill’s coal-fired boiler stack had begun to deteriorate, and the top part of the chimney needed to be replaced with a new material so the mill could continue to operate at a reasonable energy cost. As part of this six-week Green Bay Project, Tweet-Garot installed a crow’s nest and set up a temporary platform to help with the installation and welding. The stack was installed in one piece, with welding done from a basket on the crane 180 feet high up in the air.

The installation was completed in two and a half days of working around the clock, so the mill could utilize their coal-fired boiler instead of the most costly natural gas boiler. Tweet-Garot used 3/8” and 1/4” plate Corten metal on the stack.